Service: Monitoring Surveying
Project Type: Conversion
Location: Ellerdine, Shropshire
Development Costs: £160,000
Status: Completed
Self-build barn conversion to create a residential dwelling.
Our Role
- Undertook independent site monitoring for the funder through regular visits to review works completed, progress, and key risks.
- Assessed drawdown requests against the cost plan and progress on site to support fair, informed release of funds.
- Produced structured interim reports throughout, highlighting material issues, implications for completion, and any actions required.
- Completed a final review at project close-out to confirm funds could be safely released and certification/documentation was in place.
Key Considerations
- Building within the constraints of a plot shared under an existing planning permission.
- Use of Non-Material Amendment (NMA) applications to improve the scheme while maintaining compliance.
- Ecological constraints (including bats) influencing sequencing and timing of works.
Outcome
- The funder’s interests were protected through independent monitoring and clear reporting on progress, cost and key risks throughout.
Insight
Bat constraints can affect programme significantly — sequencing and mitigation requirements need to be planned early to avoid delay.
Discuss your project with us
We would be pleased to help structure and deliver your development with confidence, care and the experienced guidance your project requires.